Home >> Engineering >> Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.10.2016)

Engineering

Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.10.2016)

Description North East  Other Than North East
Total Approved Capacity  2,92,730 MT (37 Locations) 76,220 MT (9 Locations)
Financial Outlay 509.76 Crores 72.14 Crores
Capacity Completed 1,13,700(16 locations) 20,000(3 locations)
Expenditure
 
205.32 Crores

16.28 Crores
 

 

Description NE  Other Than NE  Total (NE + Other)
1. Capacity completed in FY 2012-13 2,910 - 2,910
2. Capacity completed in FY 2013-14 2,500 20,000 22,500
3. Capacity completed in FY 2014-15 43,480  - 43,480
4. Capacity completed in FY 2015-16. 64,810 - 64,810
5. Total capacity realized in 12th FYP.  1,13,700 20,000 1,33,700
6. Work in progress/is being taken up. 61080 15000 76080
a. In progress. 19410 15000 34410
b.Is being taken up. 41670 -- 41670
7. Land identified, 63620 8720 72340
a) Land taken over, agency to be fixed.  -- 3140 3140
b) land cost deposited to be handed over.  --- 5580
5580
 
c) Land found suitable,cost to be deposited  20000 --- 20000
d) Land found suitable , cost to be conveyed by state Govt.  2,500 --- 2,500
e) Land found suitable, detail for land Acquisition awaited        from State Govt. 41120 -- 41120
8. Land yet to be identified  53,500 2,500 56,000
9. Shortfall in capacity due to land availability. 830 -- 830
10. Proposal dropped due to non availability of land -- 30000 30000
Total (5+6+7+8+9) 2,92,730 76,220 3,68,950