Home >> Engineering >> Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.12.2019)

Engineering

Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.12.2019)

Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.12.2019)
       
Description North East  Other Than North East
Total Approved Capacity  3,87,160 MT (58 Locations) 1,43,220 MT (17 Locations)
Financial Outlay 509.76 Crore 72.14 Crore
Capacity Completed 1,45,210 (24 locations) 38,340 (6 locations)
Expenditure 338.93 Crore 35.86 Crore
 
       
       
       
Description NE  Other Than NE  Total (NE + Other)
1. Capacity completed in FY 2012-13 2,910 - 2,910
2. Capacity completed in FY 2013-14 2,500 20,000 22,500
3. Capacity completed in FY 2014-15 43,480  - 43,480
4. Capacity completed in FY 2015-16. 64,810 - 64,810
5. Capacity completed in FY 2016-17      3,980  3,980 
6. Capacity completed in FY 2017-18 7,930 _ 7,930
7. Capacity completed in FY 2018-19 17,100 18,340 35,440
8. Capacity completed in FY 2019-20 2,500   2,500
9. Capacity completed till date (31.12.2019) 1,45,210 38,340 1,83,550
10. Work in progress/is being taken up 55,020 41,220 96,240
a. In progress. 30,020 6,220 36,240
b.  Being taken up. 25,000 35,000 60,000
11. Land identified, 28,340   28,340
a)  Land found suitable, non- encumbrance certificate  issued by State Govt. (50% land cost deposited for Silchar/Assam)
20000   20,000
b) Land  found suitable at Zuheboto/Nagaland and Champai/Mizoram, detail for Land Acquisition awaited from State Govt. (Land cost yet to deposit)
8,340   8,340
12.Shortfall in capacity due to constraint in available land size
1,500   1,500
13. Proposal dropped  1,52,090 58,660 2,10,750
a. due to non availability of land

35,000 30,000 65,000
b. Due to funds and time constraint as per recent Ministry’s order 1,17,090 28,660 1,45,750
14. Capacity proposed for reduction due to non-identification of land
5000 5000 10,000
Total (9+10+11+12+13+14) 3,87,160 1,43,220 5,30,380