Home >> Engineering >> Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.01.2017)

Engineering

Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.01.2017)

Description North East  Other Than North East
Total Approved Capacity  2,92,730 MT (37 Locations) 76,220 MT (9 Locations)
Financial Outlay 509.76 Crores 72.14 Crores
Capacity Completed 1,17,680(16 locations) 20,000(3 locations)
Expenditure
 
209.01 Crores

16.41 Crores
 

 

Description NE  Other Than NE  Total (NE + Other)
1. Capacity completed in FY 2012-13 2,910 - 2,910
2. Capacity completed in FY 2013-14 2,500 20,000 22,500
3. Capacity completed in FY 2014-15 43,480  - 43,480
4. Capacity completed in FY 2015-16. 64,810 - 64,810
5. Capacity Completed in FY 2016-17      3,980  -  3,980 
6. Total capacity realized in 12th FYP.  1,17,680 20,000 1,37,680
7. Work in progress/is being taken up. 57,100 15,000 72,100
a. In progress. 15,430 15,000 30,430
b.Is being taken up. 41,670 -- 41,670
8. Land identified, 63,620 9,560 73,180
a) Land taken over. Tender to be invited. -- 3,980 3,980
b) land cost deposited,handing over pending by state govt. --- 5,580
5,580
 
c) Land found suitable,cost to be deposited  20,000 --- 20000
d) Land found suitable , cost to be conveyed by state Govt.  2,500 --- 2,500
e) Land found suitable, detail for land Acquisition awaited        from State Govt. 41,120 -- 41,120
9. Land yet to be identified  53,500 1,660 55,160
10. Shortfall in capacity due to land availability. 830 -- 830
11. Proposal dropped due to non availability of land -- 30000 30000
Total (6+7+8+9+10+11) 2,92,730 76,220 3,68,950