Home >> Engineering >> Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.08.2018)

Engineering

Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.08.2018)

Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 31.08.2018)
       
Description North East  Other Than North East
Total Approved Capacity  2,94,230 MT (37 Locations) 1,41,220 MT (14 Locations)
Financial Outlay 509.76 Crore 72.14 Crore
Capacity Completed 1,25,610 (20 locations) 20,000 (3 locations)
Expenditure 275.03 Crore 24.82 Crore
 
       
       
       
Description NE  Other Than NE  Total (NE + Other)
1. Capacity completed in FY 2012-13 2,910 - 2,910
2. Capacity completed in FY 2013-14 2,500 20,000 22,500
3. Capacity completed in FY 2014-15 43,480  - 43,480
4. Capacity completed in FY 2015-16. 64,810 - 64,810
5. Capacity completed in FY 2016-17      3,980  -  3,980 
6. Total capacity realized in 12th FYP.  117680 20,000 1,37,680
7. Capacity completed in FY 2017-18 7,930 _ 7,930
8. Capacity completed till date (31.08.2018) 125,610 20,000 145,610
9. Work in progress/is being taken up 59,890 24,560 84,450
a. In progress. 49,890 18,340 68,230
b.Is being taken up. 10,000 6,220 16,220
10. Land identified, 65,000 14,660 79,660
a) Land taken over. Tender to be invited. -- _ _
b) Land found suitable,non-encumbrance certificate to be issued by state govt. before deposit of cost by FCI. _ 14,660 14,660
c) Land found suitable , cost to be conveyed by state Govt.  65,000 _ 65,000
d) Land found suitable, detail for land Acquisition awaited from State Govt. _ -- _
10. Land yet to be identified _ 50,000 50,000
11. Shortfall in capacity due to land availability. 6,230 2,000 8,230
12. Proposal dropped due to non availability of land 2,500 30,000 32,500
13. Proposal under consideration for dropping of capacity due to sufficient PEG capacity. 35,000  ---  35,000 
Total (8+9+10+11+12+13) 2,94,230 1,41,220 4,35,450