Home >> Engineering >> Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 30.04.2017)

Engineering

Status of Augmentation of Storage Capacity under 12th Five Year Plan (As on 30.04.2017)

Description North East  Other Than North East
Total Approved Capacity  2,92,730 MT (37 Locations) 76,220 MT (9 Locations)
Financial Outlay 509.76 Crores 72.14 Crores
Capacity Completed 1,17,680(16 locations) 20,000(3 locations)
Expenditure
 
225.91 Crores

17.64 Crores
 

 

Description NE  Other Than NE  Total (NE + Other)
1. Capacity completed in FY 2012-13 2,910 - 2,910
2. Capacity completed in FY 2013-14 2,500 20,000 22,500
3. Capacity completed in FY 2014-15 43,480  - 43,480
4. Capacity completed in FY 2015-16. 64,810 - 64,810
5. Capacity Completed in FY 2016-17      3,980  -  3,980 
6. Total capacity realized in 12th FYP.  1,17,680 20,000 1,37,680
7. Work in progress/is being taken up. 57,100 15,000 72,100
a. In progress. 15,430 15,000 30,430
b.Is being taken up. 41,670 -- 41,670
8. Land identified, 63,620 9,560 73,180
a) Land taken over. Tender to be invited. -- 9,560 9,560
b) Land found suitable,non-encumbrance certificate to be issued by state govt. before deposit of cost by FCI. 20,000 --- 20,000
c) Land found suitable , cost to be conveyed by state Govt.  2,500 --- 2,500
d) Land found suitable, detail for land Acquisition awaited from State Govt. 41,120 -- 41,120
9. Land yet to be identified  18,500 1,660 20,160
10. Shortfall in capacity due to land availability. 830 -- 830
11. Proposal dropped due to non availability of land -- 30,000 30,000
12. Proposal under consideration for dropping of capacity due to sufficient PEG capacity. 35,000  ---  35,000 
Total (6+7+8+9+10+11+12) 2,92,730 76,220 3,68,950