Home >> Engineering >> Status of Augmentation of Storage Capacity under 12th Five Year Plan

Engineering

Status of Augmentation of Storage Capacity under 12th Five Year Plan

 

Status of Augmentation of Storage Capacity under 12th Five Year Plan i.e. from 2012-13 to 2016-17
       
Description North East  Other Than North East
Total Approved Capacity  2,92,730 MT 76,220 MT 
Financial Outlay  509.76 Crore 72.14 Crore
Capacity Completed 1,17,680 MT (18 locations) 20000 MT (3 locations)
Expenditure  (from 01.04.2012 to 31.03.2017) 225.91 crore 17.64 Crore
       
Description NE  Other Than NE  Total (NE + Other)
1. Capacity completed in FY 2012-13 2,910 - 2,910
2. Capacity completed in FY 2013-14 2,500 20,000 22,500
3. Capacity completed in FY 2014-15 43,480 - 43,480
4. Capacity completed in FY 2015-16. 64,810 - 64,810
5. Capacity completed in FY 2016-17 3,980 3,980
Total capacity completed under 12th Five Year Plan  1,17,680 20000 1,37,680

 

Status of Augmentation of Storage Capacity under extended Central Sector Scheme i.e. from 2017-18 to 2021-22
       
Description North East  Other Than North East
Total Approved Capacity as per SFC 2,27,150 MT (39 Locations) 93,220 MT (13 Locations)
Capacity to be constructed as per availablity of land made by State Government.  1,05,890 MT (15 Locations) 59,560 MT (09 Locations)
Financial Outlay 315.41Crore 104.58 Crore
Capacity Completed till date (30.04.2022) 47,530 (7 locations) 18,340 (3 locations)
Expenditure from 01.04.2017 to till 30.04.2022 Rs.171.57 Crore Rs.27.70 Crore
       
       
Description NE  Other Than NE  Total (NE + Other)
1. Capacity completed till date (30.04.2022) 47,530 18,340 65,870
a. Capacity completed in FY 2017-18 7,930 _ 7,930
b. Capacity completed in FY 2018-19 17,100 18,340 35,440
c. Capacity completed in FY 2019-20 2,500 _ 2,500
d.Capacity completed in FY 2020-21 Nil Nil Nil
e.Capacity completed in FY 2021-22 20,000 Nil 20,000
2. Work in progress/is being taken up 38,360 36,420 74,880
a. In progress. 35,020 26,220 61,240
b.  Being taken up. 3,340 10,200 13,540
i. Champai/Mizroram
(Temporary lease granted)
3,340 - 3,340
ii. Dhumka Ph. II Jharkhand
10,200 10,200
3. Land identified, 20,000  - 20,000
a)    Land found suitable, non- encumbrance certificate  issued by State Govt. (i) (50% land cost deposited for Silchar/Assam)

20000  - 20,000
4.Shortfall in capacity due to constraint in available land size
670 9,800 10,470
5. Proposal for Allotment of centre to CWC as per minutes of meeting held on 06.11.2020 by Ministry. Ministry has accorded approval for finalisation of MoU vide letter dated 05.04.21 for centres at (Zunheboto 5000 and Namsai -1670)
6,670 - 6,670
6.Proposal dropped due to funds and time constraint 1,13,920 28,660 1,42,580
Total (1+2+3+4+5+6) 2,27,150 93,220 3,20,370